Big Tech AI Data Centers: Every US Campus From Meta, Microsoft, Amazon, Google, xAI and Anthropic

By Esteve Castells

Big Tech AI Data Centers: Every US Campus, 2026
Table of contents
  1. Why big tech is building its own AI campuses
  2. The master map: big tech AI data centers at a glance
  3. Big tech AI data centers by the numbers
  4. Timeline, 2024-2026
  5. Meta data centers: Hyperion, Prometheus and five more
  6. Microsoft Fairwater and Microsoft's other AI data centers
  7. Amazon data centers and Project Rainier
  8. Google data centers: the state-by-state announcements
  9. xAI Colossus: Memphis and Southaven
  10. Anthropic data centers: what it builds and what it rents
  11. Own, lease or rent, grid or gas: how the strategies differ
  12. What this means for your AI visibility
  13. Summary
  14. Frequently asked questions

Outside the Stargate sites that OpenAI shares with Oracle and SoftBank, most of the US AI build-out belongs to six companies: Meta, Microsoft, Amazon, Google, Elon Musk's xAI (now part of SpaceX) and Anthropic. This post maps every major US campus they have announced, permitted, started or switched on, from the Hyperion data center in Louisiana to xAI's Colossus in Memphis, with location, capacity, money, power source and status as of November 15, 2026. It is the companion to our map of every Stargate site and feeds the master map of AI data centers under construction in the US.

The headline numbers: the six companies have attached public dollar figures of about $391 billion to the US campuses and state programs below, and the campus capacities they have disclosed add up to roughly 17 GW, a floor because Google and Amazon rarely publish megawatts. The largest of their campuses is Meta's Hyperion, now planned at 5 GW and more than $50 billion. The largest power plant is the Amazon-backed GW Ranch in Pecos County, Texas, permitted for 7.65 GW of gas turbines, more than any gas plant now operating in the US. Anthropic, which started with no buildings of its own, disclosed about $895 billion of compute and infrastructure commitments in the amended IPO filing it made on November 2, 2026, The Register reported.

Why big tech is building its own AI campuses

Frontier models now train on clusters too large for an ordinary data center. Most of these companies also rent from clouds and neoclouds, but the largest buyers now own their core sites, and their spending guidance shows it. Meta expects 2026 capital expenditures of $135-145 billion, including finance-lease principal. Microsoft spent $45.2 billion on capital expenditures and finance leases in the quarter to September 2026 and guided to more than $50 billion for the quarter to December. Power now sets the schedule: at least four campuses below are planned around private gas plants, and Hyperion relies on up to ten new utility gas plants.

The master map: big tech AI data centers at a glance

"Announced" means the company or a government partner published the figure; "reported" means press reporting the parties have not confirmed.

Company Main US AI campuses Largest disclosed campus Announced US build money Power approach Status, November 2026
Meta Hyperion (LA), Prometheus (OH), El Paso (TX), Lebanon (IN), Tulsa (OK), Beaver Dam (WI), Kansas City (MO) Hyperion: 5 GW, $50B+ $73B+ across six campuses Utility gas (Entergy), behind-the-meter gas in Ohio, nuclear contracts Prometheus phase 1 and Kansas City live; the rest under construction
Microsoft Fairwater Mount Pleasant (WI), Fairwater Atlanta (GA), Pecos (TX), 15 more approved in WI Pecos and the new Mount Pleasant campuses: about 2 GW each $7.3B disclosed (Wisconsin) Grid in Wisconsin; 2.67 GW private gas in Texas Two Fairwater sites operating
Amazon (AWS) Project Rainier (IN), northern Indiana, MS, PA, LA, GA, NC, two Texas sites, MO Northern Indiana: 2.4 GW $110B across seven state pledges Utility deals, nuclear off-take, 7.65 GW private gas plant Rainier operating; most others under construction or planned
Google About 20 US sites "in development" No campus MW published $111.5B across nine state pledges Utility clean-energy deals, co-located generation, fuel cells Mostly in development
xAI (SpaceXAI) Colossus 1 and 2 (Memphis), MACROHARDRR and two new Southaven sites (MS) About 2 GW target $20B+ (MACROHARDRR) Private gas turbines plus grid Colossus 2 operating and expanding
Anthropic Fluidstack sites (TX, NY), River Bend (LA), Hawesville (KY), Hubbard (TX, reported), plus hosted capacity Hawesville: 401 MW $50B program plus a $19B lease Landlord or host power First dedicated sites due 2026-2027

Big tech AI data centers by the numbers

These totals add up published figures. They mix campus budgets with multi-year statewide pledges, so each one is a floor:

  • Meta: $73 billion or more (Hyperion $50B+, El Paso $10B, Lebanon $10B+, Tulsa, Beaver Dam and Kansas City about $1B each).
  • Amazon: $110 billion (Indiana $11B plus $15B, Mississippi $25B, Pennsylvania $20B, Louisiana $18B, Georgia $11B, North Carolina $10B).
  • Google: $111.5 billion (Texas $40B, Wyoming $17B, Missouri $15B, Oklahoma, Virginia and South Carolina $9B each, Iowa $7B, Arkansas $4B, Alabama $1.5B), leaving out a $25 billion PJM pledge that overlaps Virginia.
  • Anthropic $69 billion ($50B program plus the $19B Kentucky lease), xAI $20 billion or more, Microsoft $7.3 billion.
  • Disclosed campus capacity, about 17 GW: Meta 8 GW, Microsoft about 4 GW, Amazon 2.4 GW, xAI about 2 GW, Anthropic's two leased sites about 0.65 GW. Some figures are IT load, others total campus power.
  • On-site gas generation planned or permitted: more than 13 GW (GW Ranch 7.65 GW, Kilby 2.67 GW, Hubbard 1.6 GW as reported, Southaven about 1.2 GW by xAI's figure, and Meta's Ohio plants 0.4 GW), before Entergy's utility plants for Meta.
Bar chart of announced US AI data center budgets and state pledges by company: Google $111.5 billion, Amazon $110 billion, Meta $73 billion or more, Anthropic $69 billion, xAI $20 billion or more, Microsoft $7.3 billion disclosed
Announced US campus budgets and state pledges, summed per company as of November 15, 2026. A floor: Microsoft and Google publish few campus figures.

Timeline, 2024-2026

  • 2024: xAI switches on Colossus 1 in South Memphis after a reported 122-day build. Amazon commits $11 billion in Indiana (April), Microsoft $3.3 billion in Wisconsin (May), and Meta announces the $10 billion site that becomes Hyperion (December).
  • 2025: Amazon announces Georgia, North Carolina and Pennsylvania. Microsoft pauses a $1 billion Ohio project (April) and drops Caledonia, Wisconsin (October). Louisiana approves three gas plants for Meta (August 20). Fairwater Atlanta starts (October), Meta and Blue Owl form the Hyperion venture (October 21) and Project Rainier goes live (October 29). In November, Anthropic announces its $50 billion build, Google pledges $40 billion for Texas and Amazon adds $15 billion in Indiana.
  • 2026 (year to date): xAI announces MACROHARDRR (January) and SpaceX completes its merger with xAI (February 2). Meta breaks ground in Lebanon (February), lifts El Paso to $10 billion (March) and Hyperion to 5 GW (July). Anthropic rents Colossus 1 (May). Microsoft announces Pecos and completes Fairwater Wisconsin (June). Amazon confirms GW Ranch (August), Meta reports Prometheus phase 1 complete (October) and Google announces Wyoming (November). Louisiana votes on Meta's seven new gas plants on December 10.

Meta data centers: Hyperion, Prometheus and five more

Campus Location Capacity Investment Status and date Power
Hyperion Richland Parish, LA 5 GW planned; 2 GW by 2030 $50B+ (from $10B) Under construction since Dec 2024; expanded Jul 13, 2026 Entergy: 3 gas plants approved, 7 more pending
Prometheus New Albany, OH About 1 GW; ~1M GPUs at full scale Not disclosed Phase 1 complete (Oct 2026), scaling AEP grid, 400 MW behind-the-meter gas (Williams), nuclear contracts
El Paso El Paso, TX 1 GW by 2028 $10B (from $1.5B) Under construction since Oct 2025 Not disclosed
Lebanon (LEAP) Boone County, IN 1 GW; 1,500 acres $10B+ Groundbreaking Feb 11, 2026; first capacity late 2027-early 2028 Meta pays full energy cost
Tulsa Fair Oaks Innovation Park, OK 2M+ sq ft $1B+ Groundbreaking Apr 21, 2026 PSO grid; 1,500+ MW clean energy contracted
Beaver Dam Beaver Dam, WI Not disclosed $1B+ Under construction (announced Nov 12, 2025) Meta funds ~$200M of grid work; dry cooling
Kansas City Kansas City, MO Not disclosed $1B Online Aug 20, 2025 Not disclosed

Hyperion, the Meta Louisiana data center, changed shape twice. In October 2025 Meta moved it into a joint venture with funds managed by Blue Owl, which owns 80% and shares about $27 billion of development costs while Meta leases the buildings. In July 2026 Meta raised the plan to 5 GW and more than $50 billion, with the full 5 GW around 2032.

Louisiana's Public Service Commission approved three Entergy gas plants in August 2025 and in April 2026 voted 4-1 to fast-track seven more, under a $21.37 billion application tied to what WWNO reports is a second Meta project in the parish, Project Everest. The final vote is set for December 10, and landowners sued on November 9 to void the fast-track rule, WWNO reported. Our record of US data center approvals tracks these votes.

Of the gigawatt sites, Prometheus came online first: Meta's October 2026 engineering post says phase 1 trained its Muse models. Meta also rents, through a $21 billion CoreWeave expansion signed in April 2026 and a Nebius deal worth up to $27 billion, and was reported in July to be discussing leasing up to $10 billion of its own capacity to Anthropic.

Microsoft Fairwater and Microsoft's other AI data centers

Campus Location Capacity Investment Status and date Power
Fairwater (first building) Mount Pleasant, WI "Hundreds of thousands" of Nvidia GPUs $3.3B Fully operational Jun 23, 2026 We Energies grid; 250 MW solar to match
Fairwater (second building) Mount Pleasant, WI "Similar size" $4B Under construction; due 2028 Grid
Durand Ave and International Dr Mount Pleasant, WI 15 data centers, about 2 GW Valued above $13B (reported) Site plans approved Jan 26, 2026; Durand Ave plan cut from nine buildings to seven in October 2026 We Energies, ATC
Fairwater Atlanta Atlanta, GA Not disclosed Not disclosed Operating since Oct 2025 Not disclosed
Pecos campus Reeves County, TX About 2 GW "Multibillion" over 5-7 years Announced Jun 22, 2026 Chevron's Project Kilby: up to 2.67 GW gas, first power 2028
Caledonia Racine County, WI 244 acres Not disclosed Cancelled Oct 8, 2025 Not applicable
Licking County Central Ohio Three sites $1B Paused Apr 2025; two sites kept as farmland Not applicable

Microsoft Fairwater is two operating sites joined by dedicated fiber. Microsoft unveiled the Wisconsin campus in September 2025 with a second $4 billion building and declared the first one fully operational in June 2026. In January the village board approved 15 more data centers that Microsoft expects to draw about 2 GW.

The next large Microsoft data center is in West Texas. Its Pecos campus will add about 2 GW and start on a co-located gas plant off the public grid, which Chevron is building as Project Kilby under a 20-year contract, with a final investment decision targeted for the end of 2026. Microsoft also rents from neoclouds, including a Nebius contract worth an initial $17.4 billion and about 104,000 Nvidia GPUs planned for it at Nscale's campus in Ward County, Texas.

Amazon data centers and Project Rainier

Campus Location Capacity Investment Status and date Power
Project Rainier New Carlisle, IN ~500,000 Trainium2 chips at launch $11B Activated Oct 29, 2025; Anthropic is the main user Indiana Michigan Power; Amazon pays full cost
Northern Indiana Sites not named 2.4 GW $15B Announced Nov 24, 2025 New NIPSCO subsidiary builds up to 3 GW, paid by Amazon
Mississippi Madison, Warren and Hinds counties Not disclosed $25B statewide Madison partly operating; statewide plan Apr 9, 2026 Entergy Mississippi
Pennsylvania Salem Twp (Luzerne Co.), Falls Twp (Bucks Co.) Not disclosed $20B+ Announced Jun 9, 2025 Susquehanna nuclear: up to 1.92 GW by 2032
Louisiana Caddo and Bossier parishes, Shreveport Three campuses owned by STACK $18B (from $12B) Raised Aug 18, 2026 SWEPCO; Amazon pays grid upgrades
Georgia Butts and Douglas counties Not disclosed ~$11B Announced Jan 7, 2025; under construction Not disclosed
North Carolina Richmond County 21 buildings planned $10B Groundbreaking Oct 17, 2025 Not disclosed
Pecos County West Texas GW Ranch gas plant: 7.65 GW Not disclosed Confirmed Aug 7, 2026; off-grid at start 35 turbines, built by Pacifico Energy
Somervell County Near Glen Rose, TX Not disclosed Not disclosed Site preparation (Nov 5, 2026) Direct supply from Comanche Peak nuclear plant
Montgomery County Missouri Not disclosed "Several billion dollars" Planned (Oct 30, 2026) Not disclosed

Project Rainier is the Amazon data center behind Claude. AWS switched it on in October 2025 with nearly half a million Trainium2 chips; by April 2026 Anthropic was using more than a million, and its new AWS deal secures up to 5 GW across the network. Amazon's $15 billion Indiana expansion adds 2.4 GW through a NIPSCO subsidiary that builds generation at Amazon's expense.

Amazon's largest single state pledge is $25 billion in Mississippi. In Texas it took two routes in three months: GW Ranch, a private gas plant permitted to emit more than 30 million tonnes of greenhouse gases a year, and power taken directly from the Comanche Peak nuclear plant for a campus on Vistra's land.

Google data centers: the state-by-state announcements

State Sites Announced investment Status Power notes
Texas Armstrong County; two in Haskell County $40B through 2027 (Nov 14, 2025) In development Solar and batteries beside one Haskell site
Texas Meitner Energy Center (Gray and Roberts counties); Wilbarger County Not broken out Announced 2026 Generation co-located with Intersect
Wyoming Laramie County, near Cheyenne $17B (Nov 5, 2026) Announced 702 MW of gas fuel cells with carbon capture
Oklahoma Stillwater (new), Pryor (expansion), Muskogee, Tulsa $9B over two years (Aug 13, 2025) In development Not disclosed
Virginia Chesterfield County $9B through 2026 In development Not disclosed
South Carolina Berkeley County expansion; two Dorchester County sites $9B through 2027 (Oct 13, 2025) Dorchester sites under construction Not disclosed
Iowa Cedar Rapids (new), Council Bluffs $7B (2025) In development Duane Arnold nuclear restart deal with NextEra
Arkansas West Memphis $4B through 2027 (Oct 2, 2025) In development 600 MW solar with Entergy
Missouri Two in Kansas City; New Florence (Montgomery County) $15B for New Florence (May 2026) In development 500+ MW under an Ameren capacity agreement
Alabama Jackson County expansion $1.5B for 2026-2027 Expanding TVA
Minnesota, Michigan Pine Island, Hermantown; Van Buren Township (under evaluation) Not disclosed Announced Feb-Mar 2026 Xcel adds 1,900 MW of wind, solar and storage; DTE adds 2.7 GW
Indiana, Georgia, Ohio Morgan County, Michigan City; LaGrange, Columbia County; Franklin Furnace Not disclosed Site work or plans, 2025-2026 Not disclosed

Google rarely names a megawatt figure. It announces a state, a dollar total and a utility power deal, then lists the site on its locations page, which shows about 20 US sites "in development" as of November 2026. Since 2025 it has paired many campuses with new generation contracted through the local utility: Xcel in Minnesota, DTE in Michigan, Entergy in Arkansas. Two projects break that pattern. In Texas it builds data centers and power plants together with Intersect, which Alphabet agreed to buy in December 2025, and in Wyoming its first campus will run on 702 MW of natural gas fuel cells, with carbon capture at a nearby storage hub.

xAI Colossus: Memphis and Southaven

Site Location Capacity Investment Status and date Power
Colossus 1 South Memphis, TN 300+ MW; 220,000+ Nvidia GPUs Not disclosed Online 2024; all capacity rented to Anthropic from May 2026 Grid plus batteries; 15 turbines permitted
Colossus 2 Whitehaven, Memphis, TN 110,000 GB200 plus 440,000 GB300 GPUs (Musk, reported) Site bought for ~$80M (reported) First cluster ~Jan 2026 (reported); expanding Southaven turbine plant
MACROHARDRR Southaven, MS Takes xAI to about 2 GW (Musk) $20B+ Announced Jan 8, 2026; operations planned from Feb 2026 Southaven turbine plant
"Gun Range" and "Spam" sites Southaven, MS ~420,000 GB300 GPUs Not disclosed Announced Oct 31, 2026; due Nov-Dec 2026 (Musk) Not disclosed
Southaven power plant Former Duke Energy site, Southaven, MS 41 permanent turbines, about 1.2 GW (xAI) Not disclosed Permitted Mar 2026; permit under appeal Natural gas

Colossus 2 is in Memphis, but its power comes from turbines across the state line in Mississippi, where regulators permitted 41 permanent units in March 2026. The NAACP and two local groups appealed the permit, and on October 30 a federal judge refused to dismiss the NAACP's separate Clean Air Act suit over the temporary turbines. A July 30 state order sets dates for retiring those 69 temporary units, the last by July 14, 2027.

SpaceX completed its merger with xAI on February 2, 2026, and in May it gave Anthropic all of Colossus 1's capacity; Anthropic later said its agreements also cover Colossus 2. Mississippi's governor announced the $20 billion MACROHARDRR site in January, and Musk added two more Southaven campuses on October 31.

Anthropic data centers: what it builds and what it rents

Site or deal Location Operator or landlord Capacity Money Status Type
Fluidstack custom sites Texas and New York (sites not named) Fluidstack "Gigawatts" (no total) $50B program Coming online through 2026 Own build
River Bend Louisiana Hut 8, leased to and run by Fluidstack 245 MW IT (330 MW utility); option on 1,000 MW more Not disclosed by Hut 8 Due early 2027 Leased via Fluidstack
Hawesville Kentucky TeraWulf 401 MW $19B over 20 years First capacity 2H 2027, full 2028 Leased
Hubbard (reported) Texas Nexus Data Centers 1.6 GW on-site gas plant $15B financing in talks; Google guarantee In development (reported) Leased
Project Rainier and AWS Indiana and others AWS Up to 5 GW; ~1 GW Trainium by end of 2026 $100B+ over 10 years Operating, ramping Hosted
Google TPUs Not named Google, Broadcom 1 GW+ in 2026; 5 GW of next-generation TPUs from 2027 "Tens of billions" (2025 deal) Ramping Hosted
Microsoft Azure Not named Microsoft Up to 1 GW $30B Contracted Nov 18, 2025 Hosted
Colossus 1 (plus Colossus 2 access) Memphis, TN SpaceXAI 300+ MW Not disclosed by Anthropic Online from May 2026 Hosted

Anthropic data centers are mostly other companies' buildings. Its $50 billion plan with Fluidstack (November 2025) covers custom sites in Texas and New York. Since then it has taken dedicated campuses from bitcoin miners turned developers, including a 20-year TeraWulf lease at a former aluminum smelter in Kentucky, while a Nexus campus in Hubbard, Texas, is in talks for $15 billion of debt with Google reportedly guaranteeing Anthropic's lease. The rest is hosted, including the SpaceX deal for more than 300 MW at Colossus 1.

Own, lease or rent, grid or gas: how the strategies differ

On ownership, Microsoft, Google and Amazon mostly build and own, though Amazon lets STACK own its Louisiana campuses and Microsoft also rents from neoclouds. Meta builds but put Hyperion into the Blue Owl venture, and rents from CoreWeave, Nebius and, reportedly, Google Cloud while its sites fill. Anthropic leases buildings and rents chips from all three clouds and SpaceX. xAI is so far the only one to become a landlord.

On power the split is newer. By 2026 four companies had planned campuses around private gas plants (Amazon at GW Ranch, Microsoft at Pecos, xAI in Southaven and Anthropic's landlord in Hubbard), mostly to avoid waiting years for a grid connection. Meta and Google mostly stuck with utilities that build plants the tech company pays for, with two exceptions: Meta's 400 MW of behind-the-meter gas in Ohio and Google's fuel cells in Wyoming. The utility route has fights of its own, from Louisiana's ten Entergy plants for Meta to the landowner suits over their transmission lines.

Speed drives both choices: xAI built its first Colossus cluster in a reported 122 days, Amazon took Project Rainier from announcement to activation in under a year, and Meta used fabric-covered rapid deployment structures at Prometheus. Local politics has started to push back: E&E News reported in August that Texas Gov. Greg Abbott had announced a de facto pause on data center approvals while regulators audit projects. Our tracker of moratoriums and blocked projects follows where that resistance has stopped a project.

What this means for your AI visibility

A data center now enters public debate long before it gets a vote. Residents, county officials, reporters and job seekers ask ChatGPT, Google AI Mode or Perplexity whether "the data center in Richland Parish" is approved, who is building the gas plant in Southaven or how much water a campus will use. The answer, the sources it cites (a local paper, an opposition group's site, a developer's press release, a utility filing) and its tone shape opinion before anyone reaches a public hearing.

For the companies in this post, and for the utilities, landlords and economic development agencies around them, that is a visibility question they can measure. LLM Pulse tracks brand mentions, the sources and URLs AI answers cite, share of voice and sentiment across ChatGPT, Perplexity, Gemini, Google AI Mode and Google AI Overviews, with daily, weekly or monthly tracking; Claude, Copilot, Grok, Meta AI and other models are paid add-ons. Tracking the prompts people ask about your project shows which sources the answers rely on and whether your own material is among them.

See what AI answers say about your project

Track the mentions, cited sources and sentiment that ChatGPT, Perplexity, Gemini and Google AI search attach to your brand.

View plans

Summary

Outside Stargate, Meta, Microsoft, Amazon, Google, xAI and Anthropic have announced at least $391 billion and about 17 GW of disclosed US campus capacity, led by Meta's 5 GW Hyperion in Louisiana. Amazon and Google have together spread their pledges across more than a dozen states, and Anthropic has moved from renting all of its compute to lining up dedicated campuses in Louisiana, Kentucky and Texas. The open questions for 2027 are mostly about power: Louisiana's December 10 vote on Meta's seven gas plants, Chevron's final decision on Kilby, the appeal against xAI's Southaven permit and whether GW Ranch is built at its permitted 7.65 GW.

Frequently asked questions

What is the largest AI data center big tech is building in the US?

Among Meta, Microsoft, Amazon, Google, xAI and Anthropic, the largest by disclosed capacity is Meta's Hyperion campus in Richland Parish, Louisiana, which Meta raised to a planned 5 GW and more than $50 billion in July 2026. Meta expects about 2 GW by 2030 and the full 5 GW around 2032. The largest power plant tied to a single campus is the Amazon-backed GW Ranch gas plant in Pecos County, Texas, permitted for 7.65 GW.

Where is Meta's Hyperion data center and how will it be powered?

Hyperion is near Holly Ridge in Richland Parish, northeast Louisiana, on former farmland that will exceed 3,200 acres when both phases are built. Entergy Louisiana won approval for three gas plants in August 2025 and has asked for seven more, with a final Public Service Commission vote scheduled for December 10, 2026. The commission's consultant said Meta covers the full cost of the three approved plants' turbines.

What is xAI's Colossus data center?

Colossus is xAI's AI supercomputer complex in Memphis, Tennessee, now part of SpaceX, which completed its merger with xAI on February 2, 2026. Colossus 1, in South Memphis, has been rented in full to Anthropic since May 2026, and Anthropic also has access to Colossus 2 in Whitehaven. Colossus 2 draws power from a gas turbine plant across the state line in Southaven, Mississippi, where xAI is also building the $20 billion MACROHARDRR site and two more campuses.

What is Project Rainier?

Project Rainier is the AWS AI cluster built for Anthropic, centered on an $11 billion campus in New Carlisle, Indiana. Amazon activated it in October 2025 with nearly 500,000 Trainium2 chips, and Anthropic said in April 2026 that it was using more than one million Trainium2 chips. Anthropic's 2026 agreement with Amazon secures up to 5 GW of capacity across AWS.

What is Microsoft Fairwater?

Fairwater is Microsoft's family of AI datacenters, starting with Mount Pleasant, Wisconsin, which Microsoft declared fully operational on June 23, 2026, and an Atlanta site that began operating in October 2025. The two are linked by a dedicated fiber network so they can work on one training job. A second $4 billion Wisconsin building is due in 2028, and Microsoft's next large campus is a roughly 2 GW site near Pecos, Texas, powered by a Chevron gas plant.

Does Anthropic have its own data centers?

Anthropic announced a $50 billion plan in November 2025 to build custom data centers with Fluidstack, starting in Texas and New York. It has also lined up dedicated campuses at Hut 8's River Bend site in Louisiana and at a TeraWulf site in Hawesville, Kentucky, under a 20-year, $19 billion lease. Most of its compute is still hosted by AWS, Google, Microsoft and, since May 2026, SpaceX's Colossus 1.

Where is Google building new AI data centers?

Google lists about 20 US data center sites as in development, including Armstrong and Haskell counties in Texas, Stillwater in Oklahoma, Chesterfield County in Virginia, Cedar Rapids in Iowa, West Memphis in Arkansas and Kansas City, Missouri. Its largest state pledges are $40 billion for Texas through 2027 and $17 billion for its first Wyoming campus, announced in November 2026. Google rarely publishes megawatt figures for individual campuses.

Why are tech companies building their own gas plants for data centers?

Mostly to avoid waiting years for a grid connection. Amazon at GW Ranch, Microsoft near Pecos, xAI in Southaven and Anthropic's landlord in Hubbard, Texas, all plan campuses around on-site gas generation. Critics point to the emissions, and xAI's Southaven permit is under appeal while a Clean Air Act suit over its temporary turbines continues.